Paradise Road Reconstruction Between Sahara and Las Vegas Blvd Begins April 22

Paradise Road Reconstruction Between Sahara and Las Vegas Blvd Begins April 22

Drivers should expect single-lane traffic and a St. Louis Avenue closure at Paradise Road through May 1.

A pavement reconstruction project on Paradise Road and St. Louis Avenue between Sahara Avenue and Las Vegas Boulevard began Wednesday, April 22, and is scheduled to continue through Friday, May 1, 2026. The $500,000 project, managed by the city of Las Vegas and funded by the Regional Transportation Commission Fuel Indexing Tax, will restrict traffic to one through lane in each direction for much of its duration.

Lane Restrictions and Road Closures in Effect Through May 1

Traffic on Paradise Road between Sahara Avenue and Las Vegas Boulevard will generally be limited to one through lane for both northbound and southbound travel during the project window. St. Louis Avenue will be fully closed at Paradise Road during the milling and paving phase of the work.

Work activities are scheduled between 7 a.m. and 5 p.m., Monday through Friday. Milling and paving operations are set to begin Monday, April 27, and are expected to take approximately three days, subject to weather and equipment availability.

Scope of Work: Utilities, Paving, and New Lane Striping

Primary work activities include lowering utilities, milling, dense-grade paving, raising utilities, and the installation of new lane striping. Preliminary work has already been completed, consisting of improvements to sidewalk areas to meet federal requirements under the Americans with Disabilities Act, including the reconstruction of concrete cross gutter, curb, and gutter.

Amrize, Inc. is the contractor on the project. The city of Las Vegas is managing the work, which carries an estimated cost of $500,000 funded by the Regional Transportation Commission Fuel Indexing Tax.

Recommended Alternate Routes for Drivers

The city is recommending Sahara Avenue and Oakey Boulevard as alternate routes for east- and westbound traffic affected by the construction. Drivers traveling north or south are advised to use Las Vegas Boulevard as an alternate corridor.

Motorists in the area near the Strip corridor should plan for delays and allow additional travel time through the end of the project period on May 1.

What we know

  • The pavement reconstruction project on Paradise Road and St. Louis Avenue runs from April 22 through May 1, 2026.
  • Traffic will generally be restricted to one through lane for northbound and southbound travel on Paradise Road.
  • St. Louis Avenue will be closed at Paradise Road during the milling and paving portion of the project.
  • Milling and paving operations are scheduled to begin April 27 and will take approximately three days.
  • The estimated project cost is $500,000, funded by the Regional Transportation Commission Fuel Indexing Tax.
  • Amrize, Inc. is the contractor; the city of Las Vegas is managing the project.
  • Preliminary work included ADA-compliant sidewalk improvements, concrete cross gutter, curb, and gutter reconstruction.
  • Work hours are 7 a.m. to 5 p.m., Monday through Friday.

Why it matters

Paradise Road is a major north-south arterial running parallel to the Las Vegas Strip, serving both residents and the heavy tourist and commercial traffic that defines the corridor between Sahara Avenue and Las Vegas Boulevard. Lane restrictions and a localized street closure at St. Louis Avenue have the potential to create significant delays for commuters, hotel workers, and visitors navigating one of the city's busiest zones. The project's ADA upgrades also signal a broader effort to bring aging infrastructure into compliance with federal accessibility standards.

What’s next

Milling and paving operations are scheduled to begin Monday, April 27, and are expected to last approximately three days, subject to weather and equipment availability. The full project is set to conclude by Friday, May 1, 2026. Drivers are advised to monitor conditions and use the recommended alternate routes — Sahara Avenue, Oakey Boulevard, and Las Vegas Boulevard — until work is complete.

Frequently asked questions

When does the Paradise Road construction project start and end?

The project began Wednesday, April 22, 2026, and is scheduled to run through Friday, May 1, 2026.

What roads are affected by the Paradise Road repaving project?

Paradise Road and St. Louis Avenue between Sahara Avenue and Las Vegas Boulevard are impacted. St. Louis Avenue will be closed at Paradise Road during the milling and paving phase.

What are the recommended alternate routes during the Paradise Road construction?

Sahara Avenue and Oakey Boulevard are recommended for east- and westbound traffic, while Las Vegas Boulevard is recommended for north- and southbound travel.

How much does the Paradise Road reconstruction project cost?

The estimated cost of the project is $500,000, funded by the Regional Transportation Commission Fuel Indexing Tax.

What hours will construction work take place on Paradise Road?

Work activities are scheduled between 7 a.m. and 5 p.m., Monday through Friday, for the duration of the project.